1984-02-21 - Resolution 1984-10 - ACCEPTING AN AGREEMENT FOR SUPPLEMENTAL PHASE 1 ENGINEERING SERVICES FOR THE PHASED IMPROVEMENT OF BG RD FROM LAKE-COOK TO IL. RT. 83RESOLUTION NO. 84-10
A RESOLUTION ACCEPTING AN AGREEMENT FOR SUPPLEMENTAL PHASE I ENGINEERING
SERVICES FOR THE PHASED IMPROVE;'IENT OF BUFFALO GROVE ROAD FROM LAKE-COOK
ROAD TO IL. RT. 83
WHEREAS, the President and Board of Trustees of the Village of
Buffalo Grove desire to cause the implementation of the phased improvement
of the intersection of Buffalo Grove Road and Il. Rt.83, and;
WHEREAS, the approval of an agreement with a consulting engineer
is required in order to proceed with the necessary engineering of the
project;
NO[,J, THEREF0RE, BE IT RES0LVED by the President and Board of
Trustees of the Village of Buffalo Grove, Lake and Cook Counties, Illinois
that the President and Clerk be, and they are hereby authorized and directed
to execute the letter agreement dated February 9, I9B4 re: "Buffalo Grove
Road/Il. 83 Intersection Improvement" which relates to the phased improvement
of Buffalo Grove Road from Lake-Cook Road to Il. Rt. 83. A copy of said
letter agreement is attached hereto and made a part hereof.
AYES:
NAYES:
ABSENT:
PASSED:
6 Marienthal, Stone, OrRei1ly, Hartstein, clover, Reid
0 None
0 None
February 2l 1984
AP PROV ED
age res i den t
ATTEST
VJ a ge C erk Pro Tem
\J
Midwest Consulting Engineers, lnc.
5151 North Harlem Avenue . Chicago, lllinols 60656. (312) 792-11m
February 9, 1984
Mr. Gregory P. BoysenDirector of Publi-c WorksVillage of Buffalo Grove
50 Raupp BoulevardBuffalo Grove, Illinois 60090
Reference: Buffalo crove Rd. /IL. 83Intersection Improvement
Dear Mr. Boysen:
work Item
Enclosed is our Proposal /Agreement to furnish Engineering Ser-vices for preparation of the Addendum to the EnvirorimentalAssessment and Combined Report for Buffalo Grove Road fromLake-Cook Road to Aptakisic. The Addendum is reguired todocument the decision and receive IDOT appioval tostage-construct the improvement by constructing only the IL. g3
intersection with the 3-lane approaches at this-tj.me.- The scopeof work is outl-ined below.
Manhou r s Requi red
Traffic and Capacity AnalysisPrepare Intersection DesignStudy Plan
Prepare Addendum Report
The fee for this work willIabor costs times a factorbenefits and profit. TheS1,683, developed as folLows:
32
L2
AE
on the basis of actualc-over overhead, fringefor the work will tie
4
Tota I
be chargedof 2.7 2 to
maximum fee
48 manhours x S12.75 avg. salary rate x 2.72 = $1,6g3
Mr. Gregory P. BoysenDirector of Public WorksFebruary 9, 1984
Page 2
The Addendum will be completed no later than March 14, lgg4,based on receiving Village authorization by February 22, L9g4.
If this Proposal /Agreement isreturn one (1.) copy to us.
acceptable, please sign below and
Very truly yours,
Midwest Consulting Engineers, Inc.
rJH/dh- 2 0
Enc 1o sure
Accepted By:
Date 2 Z z/
+*^))+-",**.
Thomas J. Hi{fter