2004-01-07 - Appearance Review Team - Minutes Board or Commission: ❑Appearance Review Team
Document Type: ❑Agenda 0 Minutes
Meeting Date: 01/07/2004
Type of Meeting: ❑ Regular Meeting
Appearance Review Team (ART) Meeting
8:30 p.m., 1/7/2004
Proposed Townhomes, East Side of Prairie Road at Chestnut Terrace
Petitioner: John Green, Groundwork Limited, for Insignia Homes
ART TEAM:
Steve Trilling, Trustee Liaison to the Plan Commission
Denice Bocek, Plan Commissioner
Matthew Cohn, Plan Commissioner
Robert Pfeil, Village Planner
Greg Summers, Associate Planner
ALSO PRESENT:
John Green, Groundwork, Limited
Alan Scimeca, Insignia Homes
CC:
Jeff Berman, Trustee Liaison to the Plan Commission
Plan Commission
SUBJECT SITE
East Side of Prairie Road at Chestnut Terrace (immediately north of Mirielle Phase II)
PETITIONER REQUEST
Petitioner John Green, Groundwork Limited (on behalf of Insignia Homes), is seeking consolidation of
four parcels on the east side of Prairie Road at Chestnut Terrace (immediately north of Mirielle Phase II),
and approval of an R-8 Planned Unit Development. The plan proposes the removal of the current single
family residences and related structures and construction of 41 new townhome units including associated
streets, walks, water retention, and recreational features.
ART RECOMMENDATION / NOTES
Mr. Green provided an overview of the project and noted that the Appearance Review Team (ART) is
seeing the same site plan presented at the first Plan Commission workshop on December 3, 2003. He
noted that in his most recent submittal for the second Plan Commission workshop certain elements have
been modified. Those elements include a fence along Prairie Road, eliminating the street connection to
Avalon Drive (making it emergency access only), and rotating Building 11 to be parallel to Chestnut
Terrace.
The current plan proposes a mix of two basic units ("A" and "B") each available in interior and end unit
floor plan. Each of these four different configurations has been designed to achieve a unique exterior
elevation.
Mr. Green stated that he has received positive feedback on the mix of brick and stone used at the
Noah's Landing development. For that reason he is again proposing a mix of brick, and stone.
Fireplaces will be optional, but he indicated that when a unit purchaser does elect to have a fireplace the
chimney will be clad in stone. On the interior units the fireplace chimneys would always be located at the
two story portions of the building where adjacent units meet. On the end units the fireplace and chimney
would be available at either the rear corner or on the side, with resulting effect on the elevations. The
fireplaces will be interior with an exterior flue that is 2.5 feet wide and will carry down to the foundation of
the building. None of the elevations presented to the ART depict any chimneys, so possible appearance
issues have not been identified nor discussed. Mr. Scimeca indicated the fireplace upgrade would likely
cost approximately$8,000.
Mr. Green stated he believes the color tonality of the building exteriors is too close on the Noah's
Landing development and he is trying to achieve a broader range of tones for this development. One
color palette contains the darker colors whereas the other has more contrast and more whites. Both
schemes propose use of a king-size brick for consistency with the size of the square cut stone. The color
schemes will alternate from one building to the next as well as across the street from one another. ART
members expressed concern that the color schemes were still too close in tone and that the range should
be broader. Mr. Green agreed to explore more diverse color schemes for the buildings.
The ART members noted that the units are arranged in only two different building layouts and the
potential for monotony is problematic. Only"ABAB" and "AAB" buildings are depicted on the plans. The
ART asked if other unit configurations ("ABBA," "BARB," "BBA," "ABA," "BAB") are feasible. Mr. Green
responded that the units are designed to fit together and it is not always possible to reconfigure the units
in a specific building. He did indicate they can flip Buildings 6 and 7 to alleviate the "ABAB" repeat as
one drives down Chestnut Terrace.
Mr. Scimeca stated that the proposal includes casement windows without muntins although the muntins
issue is subject to change. Mr. Green stated that muntins can create long term maintenance issues in
which some windows do and some do not have the muntins installed.
ART members asked about the different types of garage doors and garage door headers. Mr. Green
suggested that the next submittal be modified to include arched headers with no windows in the brick
garage entries and flat headers with arched windows in the door on the stone garage entries.
Changes have been incorporated into the garage/gable/bedroom portions of the front elevations to
provide more articulation on the front fagade . Stone bays have been incorporated into the rear of the
buildings to create a more consistent mix of stone, brick, and cementitious siding material on all four
elevations of a building. Some team members supported adding brick on the rear elevation while other
felt the brick might overwhelm that elevation of the building.
ART members inquired what the price point will be for the units in this development. Mr. Scimeca
indicated that the marketing sign will probably read "starting from $349,900" but with upgrades the
average unit will cost over$400,000.
The meeting adjourned at 9:45 p.m.