BIDTAB Watermain Improvements 2017Client: Village of Buffalo Grove
Project: Mohawk Court - Watermain
GHA Project No: 4798.021
Project Manager:Brian Wesolowski
$234,761.31
$265,565.00
$206,230.00
$244,265.00
$227,746.26
$257,495.00
$185,000.00
$276,550.00
$218,352.00
$229,840.00
$180,059.00
$282,245.00
$236,782.00
$244,072.25
Contractor
Alamp Concrete
Berger Excavating
Bolder Contractors
Mancini Contractors
Maneval Construction
ENGINEER'S ESTIMATE
H. Linden & Sons
J. Congdon Sewer
Joel Kennedy Construction
John Neri Construction
Lenny Hoffman Excavating
Martam Construction
Mauro Sewer
Patnick Construction
Sheridan Plumbing
Swallow Construction
Campanella & Sons
Copenhaver Construction
Gerardi Sewer & Water
Glenbrook Excavating
$50.00
Gewalt Hamilton
2/2/17
Village of Buffalo Grove
Fee:
Payable To:
Bid Opening:
Bid Opening Location:
$206,130.00
BID RESULTS
Bid (As-Read)
$264,270.00