Fire 27 Roof Bid Tab 2015IRS
CONTRACTOR Metalmaster
Roofmaster
CSR Roofing
Contractors, Inc.
All American
Exterior Systems
Filotto Construction
Inc.IRS Phase 1 Estimate
BASE PRICES
BASE BID: (24 Gauge Prefinished Galvanized Metal Roof System)$172,779.00 $262,700.00 $324,000.00 $324,580.00
ALLOWANCE: (Funding of Unit Price Items)$15,000.00 $15,000.00 $15,000.00 $15,000.00
TOTAL BID (Base Bid + Allowance)$187,779.00 $277,700.00 $339,000.00 $339,580.00 $202,000 - $252,000
ALTERNATE BID #1: (0.040” Prefinished Embossed Aluminum Metal
Roof System)$187,683.00 $277,900.00 $338,000.00 $348,780.00
ALLOWANCE: (Funding of Unit Price Items)$15,000.00 $15,000.00 $15,000.00 $15,000.00
TOTAL ALTERNATE BID #1 (Alternate Bid #1 + Allowance)$202,683.00 $292,900.00 $353,000.00 $363,780.00 $202,000 - $252,000
ALTERNATE BID #2: (Vented Shingle Roof System)$144,423.00 $313,000.00 $230,685.00 $299,400.00
ALLOWANCE: (Funding of Unit Price Items)$15,000.00 $15,000.00 $15,000.00 $15,000.00
TOTAL ALTERNATE BID #2 (Alternate Bid #2 + Allowance)$159,423.00 $328,000.00 $245,685.00 $314,400.00 $202,000 - $252,000
ALTERNATE ADD #1: (Prefinished Galvanized Sheet Metal Fascia
Cladding)$9,987.00 $8,000.00 $19,900.00 $8,500.00 $15,000.00
ALTERNATE ADD #2: (Prefinished Embossed Aluminum Sheet Metal
Fascia Cladding)$12,473.00 $10,000.00 $24,500.00 $10,500.00 $15,000.00
UNIT PRICING
Replace steel roof decking (per sq. ft.)$8.99 $15.00 $8.00 $10.00
Repair and rust paint steel roof decking (per sq. ft.)$7.50 $16.00 $4.75 $8.00
Replace & paint 1” x 4” cedar fascia (per lineal foot)$17.99 $8.00 $6.50 $10.00
Replace & paint 2” x 10” cedar fascia (per lineal foot)$20.99 $13.00 $13.00 $12.00
Replace 2” x 6” wood blocking (per lineal foot)$8.99 $8.00 $4.75 $8.00
Replace 2” x 8” wood blocking (per lineal foot)$9.49 $9.00 $6.25 $8.00
Replace 3/4” x 6” plywood blocking (per lineal foot)$10.99 $5.00 $4.00 $6.00
Time & Material
Roofer -Time per-man-hour 125.00$ 120.00$ 110.00$ 107.00$
Material cost plus %15%15%25%10%
Carpenter -Time per-man-hour 150.00$ 120.00$ 115.00$ 110.00$
Material cost plus %15%15%25%10%
SCHEDULE
Commence Work in Days 30 30 30 30
Completion Work in Days 11/6/2015 11/6/2015 11/6/2015 11/6/2015
Acknowledge Receipt of Addendum 1&2 Y/N Y Y Y Y
Bid Bond Y/N Y Y Y Y
Attachments Y/N Y Y Y Y
Bids Due: Wednesday, July 22, 2015 at 10:00 AM
VILLAGE OF BUFFALO GROVE
FIRE STATION #27
ROOF REPLACEMENT
IRS JOB # 15449